Australia’s largest datacentre operator NextDCs shares dive as Melbourne expansion delayed
Confidence88·multiple reportsImportance92NP-EVT-20261021-D912793
NextDC has told investors that its plans to double the size of its west Melbourne datacentre has hit an obstacle in community objections to 22m high power poles Australia’s largest datacentre operator has been forced to delay the controversial expansion of its M3 site in Melbourne’s west amid a pause in construction of new 22m power poles following community protest. On Wednesday, NextDC told the Australian Stock Exchange that delays to electricity provider Jemena’s upgrade of the power poles
Read the original at the primary source
Australia’s largest datacentre operator NextDCs shares dive as Melbourne expansion delayed
Josh Taylor Technology reporter · 10/21/2026, 4:58:25 AM